In situ remediation started

04 April 2013

The in-situ installation is operational since April 2013: SVE is active in the whole area, MPE around the excavation pit and in the tank farm and perozone injections occur in the ‘drum storage area’.

During the in-situ remediation process parameters such as extracted vapour, ambient air and in- and effluent water are intensively monitored.

Life

Our Partners

Coordinating beneficiary

Vopak

Associated beneficiary

RSK Group PLC

Badeco

Progress

First phase of in-situ remediation completed. Second phase of in-situ remediation on-going, ISCO and SVE operational.