First monitoring results available

30 September 2013

The preliminary monitoring results show no unexpected values. The PID-values in the extracted vapour range from 30-60 (SVE) to 2000-5000 (MPE). Mostly chlorinated ethanes and volatile petroleum hydrocarbons are extracted.

At the surface near the injection wells and in the sewers PID and LEL measurements show no high values and no elevated concentrations of O3 are detected. So far there is no indication of any safety problems related to the ISCO.

Life

Our Partners

Coordinating beneficiary

Vopak

Associated beneficiary

RSK Group PLC

Badeco

Progress

First phase of in-situ remediation completed. Second phase of in-situ remediation on-going, ISCO and SVE operational.