Remediation goals reached in former drum storage area

31 October 2013

The evolution of the groundwater concentrations in time is illustrated in the charts below. The blue lines indicate the concentrations in the 4 monitoring wells. The red lines show the remediation goals as defined in the RAP. As can be seen from the charts, the remediation goals for several parameters were already achieved after only 4 months of ISCO. The final goals are currently reached, about half a year after the start of the in-situ remediation.

Life

Our Partners

Coordinating beneficiary

Vopak

Associated beneficiary

RSK Group PLC

Badeco

Progress

First phase of in-situ remediation completed. Second phase of in-situ remediation on-going, ISCO and SVE operational.