First phase of in situ remediation successfully completed

28 November 2013

No emissions of ozone and/or VOC’s and no subsidences have been detected during the perozone injections. There were no H&S-issues during the remediation of the drum area.

The ISCO and SVE in the former drum storage area were terminated in November 2013. Monitoring of the groundwater concentrations will be continued to ensure that the situation is stable.

Life

Our Partners

Coordinating beneficiary

Vopak

Associated beneficiary

RSK Group PLC

Badeco

Progress

First phase of in-situ remediation completed. Second phase of in-situ remediation on-going, ISCO and SVE operational.