ISCO restarted

19 June 2014

The first measurements in the extracted air, the monitoring wells and the sewer show the absence of ozone and VOC emissions. The safety and process parameters will be monitored on a regular basis.

The first groundwater monitoring is scheduled in August 2014.

Life

Our Partners

Coordinating beneficiary

Vopak

Associated beneficiary

RSK Group PLC

Badeco

Progress

First phase of in-situ remediation completed. Second phase of in-situ remediation on-going, ISCO and SVE operational.