Preparation of the in situ remediation in the big source area in the tank farm

10 August 2015

Since a safe situation was observed and confirmed during the injections in the small source area in the tank farm, the preparation of the fourth phase of the in situ remediation has started.  The fourth phase is the perozone injections in the big source area inside the operational tank farm. 

Four soil vapour monitoring wells are installed at the border of the two storage tanks (T60 and T62) next to the perozone injection points.  Ozone and VOC concentrations will be measured in these vapour monitoring wells during the remediation.  

Life

Our Partners

Coordinating beneficiary

Vopak

Associated beneficiary

RSK Group PLC

Badeco

Progress

First phase of in-situ remediation completed. Second phase of in-situ remediation on-going, ISCO and SVE operational.