RAP submitted

08 July 2011

Final remedial action plan has been submitted to the Flemish authorities (OVAM).  OVAM's approval is expected end October 2011.

The remediation concept comprises a combination of in situ chemical oxidation (ISCO), multi-phase extraction (MPE) and excavation.

in the areas without indications of pure product ISCO with perozone will be applied as stand-alone technology wiyh MPE as fall-back technology.

The area outside the tank farm with indications of pure product (source area) will be treated by excavation followed by ISCO. The excavation is foreseen until 2 m-bgl and the excavated soil will be transported to an off-site treatment centre.

Life

Our Partners

Coordinating beneficiary

Vopak

Associated beneficiary

RSK Group PLC

Badeco

Progress

First phase of in-situ remediation completed. Second phase of in-situ remediation on-going, ISCO and SVE operational.